SERVICING REFRIGERATION COMPONENTS
Any technician attending the machine for any purpose must be
a fully qualified refrigeration engineer.
WARNING: Before doing any work on the machine ensure that
the power is switched and locked off and that all isolators are
tagged. If a refrigerant circuit is opened, it must be evacuated,
and recharged, after ensuring that the refrigerant is clean and
free from impurities, the filter-drier has been changed and the
unit has been tested for leaks. Before any operation on a
refrigerant circuit, the complete unit refrigerant charge must
be removed with a refrigerant charge recovery group.
General maintenance
Keep the unit itself and the space around it clean and free of
obstructions. Remove all rubbish such as packing materials, as
soon as the installation is completed.
Regularly clean the exposed pipework to remove all dust and
dirt. This makes detection of water leaks easier, and they can
be repaired before more serious faults develop.
Confirm that all screwed and bolted connections and joints are
secure. Secure connections prevent leaks and vibration from
developing.
Check that all insulation joints are securely closed and that all
insulation is firmly in place. Check all heat exchangers and all
pipework.
Confirm regularly that any phase imbalance in the three-phase
power supply is within acceptable limits.
Lubricate the hinges, locks and latches on the electrical control
box doors sparingly.
Liquid refrigerant charging
Checking the charge
WARNING: When adjusting the refrigerant charge always
ensure that water is circulating in the evaporator in order to
prevent any possibility of freezing up. Damage caused by
freezing is not covered by the product warranty.
30GV and 30GY units are shipped with a full normal charge of
refrigerant. Refer to the Physical Data table. If it is nevertheless
necessary to add more refrigerant, run the unit at full capacity
for some time and then add refrigerant until there are no
bubbles in the sight glass. This will generally mean adding
more refrigerant than would be needed to prevent bubbles from
being seen in the sight glass.
WARNING: To ensure proper operation of 30GV and 30GY
units there must be at least 5 K of subcooling as the liquid
refrigerant enters the expansion valve.
30GV and 30GY units use a halogen refrigerant. For your
information, please find below an extract from the official
publication dealing with the design, installation, operation and
maintenance of air conditioning and refrigeration systems and
the training of people involved in these activities, as agreed by
the air conditioning and refrigeration industry.
Refrigerant guidelines
Refrigeration installations must be inspected and maintained
regularly and rigorously by specialists. Their activities must be
overseen and checked by properly trained people. To minimise
discharge to the atmosphere, refrigerants and lubricating oil
must be transferred using methods which reduce leaks and
losses to a minimum.
Leaks must be repaired immediately
A valve on the condenser liquid refrigerant outlet line
enables the refrigerant charge to be transferred to the
receiver provided specifically for this purpose.
If the residual pressure is too low to make the transfer
alone, a purpose-built refrigerant recovery unit must be used.
Compressor lubricating oil contains refrigerant. Any oil
drained from a system during maintenance must therefore
be handled and stored accordingly.
Refrigerant under pressure must never be discharged to
the atmosphere.
Recharging liquid refrigerant (30GV units)
CAUTION: 30GV 020 to 059 units are charged with liquid
HFC-407c refrigerant.
This non-azeotropic refrigerant blend consists of 23% R-32,
25% of R-125 and 52% R-134a, and is characterised by the fact
that at the time of the change in state the temperature of the
liquid/vapour mixture is not constant, as with azeotropic
refrigerants. All checks must be pressure tests, and the
appropriate pressure/temperature ratio table must be used for
the interpretation of the values.
Leak detection is especially important for units charged with
refrigerant R-407c. Depending on whether the leak occurs in
the liquid or in the vapour phase, the proportion of the different
components in the remaining liquid is not the same.
NOTE: Regularly carry out leak checks and immediately repair
any leak found.
Undercharge (30GV units)
If there is not enough refrigerant in the system, gas bubbles
appear in the moisture sight glass. There are two possiblities:
Small undercharge (bubbles in the sight glass, no
significant change in suction pressure).
- After detection and repair the unit can be recharged.
- The replenishment of the charge must be done in the
liquid phase at the liquid line. The refrigerant cylinder
must contain a minimum of 10% of its initial charge.
Significant undercharge (large bubbles in the sight glass,
drop in suction pressure).
- Small units (charge below 20 kg per circuit).
After detection and repair completely drain the
refrigerant charge, using a refrigerant recovery unit,
then recharge completely, following the precautions
given above.
- Large units (charge above 20 kg per circuit).
After detection and repair completely recharge the
unit as described above, operate it for a few minutes
and then let a specialist carry out a chromatographic
analysis to verify the composition of the blend (range:
R-32: 22-24%, R-125: 23-27%, R-134a: 50-54%).